• The operation of the EGHPP will contribute to the central energy system of Mongolia hence it will be independent from foreign countries.
  • Egiin Goliin Hydro power plant will be the 1st high capacity hydro power plant in Mongolia.
  • In 2015, total demand of electricity will exceed over supply.
  • Egiin Goliin hydro power plant is one of the highly possible variation which can replace import of electricity.
  • Central energy system of Mongolia imports annually $ 25 mln of electricity.
  • Egiin Goliin hydro power plant will guarantee the national security of electricity.
  • According to the geological study, the EGHPP geological condition of the dam foundation is found to be very agreeable.
  • In November 2013, the Government of Mongolia passed resolution to start the construction of Egiin Goliin hydro power plant.
  • Over the years total cost of the building power plant is increasing.
  • The EGHPP is located at the confluence of Egiin and Selenge river 2.5km upstream.
  • Construction of EGHPP will open opportunities of farming the water birds, fish and sable breeding.
  • To fill the reservoir with water during summer and to generate electricity during winter.
  • In the area of Egiin Goliin hydro power plant, annual precipitation is between 300 and 310 mm.
  • In the area of Egiin Goliin hydro power plant, average temperature in December is -40 C, in July and August are +25 C.
  • An ice phenomena of EGHPP, will be at its highest in December will reach 1.5m.
  • In the area of Egiin Goliin hydro power plant, mean wind speed is 2.3 m/sec, humidity level is 72%.
  • Since 1977, Mongolia paid $311 mln which equals to 451 bln of tugrugs on electricity imported from Russian Federation.
  • Start up minutes of hydro power plant is 2-5 minutes in contrast to Thermal power plant 2-4 hours.
  • Central energy system’s daily load during the winter is 776-800 MW.
  • The EGHPP generated energy will be connected to the CES via 2 circuits double conductors with capacity of 220 kV.
  • The main criteria for meeting the environmental objective are avoided of carbon dioxide (CO2) emissions, and the specific carbon offset of the project is determined in terms of carbon dioxide (CO2) emissions avoided per GWh over the lifetime of the project and thus EGHPP reduces 709 thousand ton of CO2 annually.
  • By 2022,EGHPP is to produce 581 million kWh annually at minimum and the annual electricity generation is to vary between 581 to 2662 million kWh.
  • By the April 2014 investigative study discovered 218 artifacts at the hydropower plant DAM SITE (910м), and 24 artifacts at the infrastructure route.
  • 242 artifacts are planned to be excavated and preserved in 2014-2015.
  • 423 species of plants grow at the Egiin Goliin DAM SITE.
  • Hydropower costs less than most energy sources.
  • Renewable Energy creates three-times more jobs than fossil fuels.
  • In 1878 the world's first hydroelectric power scheme was developed at Cragside in Northumberland, England by William George Armstrong.
  • Hydropower today provides about 20 % of the world's electricity and is the main energy source for more than 30 countries.
  • Hydropower facilities can quickly go from zero power to maximum output, making them ideal for meeting sudden changes in demand for electricity.
  • Hydropower can also be used for water supply, flood control, irrigation and even recreation purposes.
  • The financial status of the hydroelectric industry is generally healthy due to long equipment life and low maintenance and operating costs.
  • Egiin Goliin hydropower plant is estimated to cover the investment in 20-25 years of time with its sales income.
  • Thermal power plants in UB city burns 3.5 million tons of raw coal, pollutes the air with 4 tons of coal, 4.5 million cubic meters of gas and 6kg emissions of sulfur gas.
  • The Eg river is Mongolia's third largest river, and at the proposed dam site has a catchment area of about 40,000 km².
  • Due to Mongolian country characteristics and situation, the value of 315 MW installed capacity has been selected.
  • There are 21 types of fish at the Eg river.
  • The new bridge that will be built across River Selenge will be a steel concrete bridge.
  • Turbines and generators are expected to be replaced after 32 years of operation.
  • Peak demand of the Mongolian energy system reached 948 MW, exceeding both installed and feasible generation capacity and the reason for increased imports of electricity
  • Electricity is imported from Russia to the Central Region Integrated System via Selendum sub-station Russia and Darkhan sub-station Mongolia.
  • BACK
  • HISTORICAL AND CULTURALY-ARCHAEOLOGICAL STUDIES
  • PREVIOUS STUDIES
  • The national and international joint research was conducted in Valley of Eg River between 1991 to 2002 and protected and rescued 139 historical findings. There was informed by the professional organizations to protect remained memories.

  • UPDATED FIELD INVESTIGATION
  • Due to the location of previously discovered findings are not clear and values are different, new investigation was needed. The joint research team of the Archaeological institute of Academy of Science, Archaeology- anthropological faculty of Ulaanbaatar University, Archaeology-ethnology expedition at the Science Technological university conducted archaeological investigation and study in reservoir area and along the corridor of access road and power transmission line in accordance with clause 27.8 of the Law on Cultural heritage Protection. There are 416 memories (up to 910 m a.s.l) in reservoir area, 24 memories along access road and transmission line were registered and documented in result of this investigation and study.

  • Contractor
  •  INSTITUTE OF HISTORY AND ARCHAEOLOGY, MONGOLIAN ACADEMY OF SCIENCES

    Тус хүрээлэн нь жил бүр хэдэн арван үндэсний хээрийн шинжилгээний ангиудыг зохион байгуулж Монгол орны нийт нутаг дэвсгэрийн хэмжээнд археологийн хайгуул, малтлага судалгааны ажлыг хийдэг юм. Мөн ОХУ, Япон, АНУ, БНСУ, Итали, Франц, Герман, Турк, Монако, Швейцар, Бельги зэрэг гадаадын 10 гаруй орны хориод хүрээлэн, мөн тооны их дээд сургуулиудтай хамтарсан судалгаа шинжилгээ явуулж Монголын түүх-соёлын өвийг дэлхийд таниулан сурталчилахад багагүй хувь нэмэр оруулж байна. Эгийн голын УЦС төслийн нэгж нь тус хүрээлэнтэй төсөл хэрэгжих орон нутаг болох Эгийн голын сав газарт байгаа түүхийн дурсгалт зүйлсийг авран хамгаалах чиглэлээр хамтран ажиллаж байна.

  •  BUSINESS ADMINISTRATION AND HUMANITIES HIGH SCHOOL, MUST

    The School of Social Technology with the mission to prepare and shape young generation with a high culture, education and awareness performs its activities conducting archaeological explorations and excavation studies. Egiin Goliin HPP project unit has been working together with this school to rescue and protect historical relics found at the DAM SITE in the Eg river basin.

  •  ULAANBAATAR UNIVERSITY

    The School of Social Technology with the mission to prepare and shape young generation with a high culture, education and awareness performs its activities conducting archaeological explorations and excavation studies. Egiin Goliin HPP project unit has been working together with this school to rescue and protect historical relics found at the DAM SITE in the Eg river basin.

  •  МОNGOLIAN NATIONAL MUSEUM

    Mongolian National Museum is a leading national museum which has 10 exhibition halls possessing treasures consisted of 50000 exponents which briefly shows history, culture, heritage, ethnography, traditional customs of nomads from the prehistoric age when people started living in the land of Mongolia right to the present day. Mongolian National Museum is the Central Scientific Research and Advertising organization where stores over 30% of the whole treasures of all museums of the country and displays it to public. The Egiin Goliin HPP project unit has been working together with this museum with an aim of rescuing and protecting historical relics found in the basin of the Eg river.

  • Date:  2014.06.01 - 2014.07.31
  • PROGRESS OF RESCUING WORKS:
  • - The following professional organizations related to archaeology conducted rescuing work of historical and cultural finding in 2014-2015 in project related area:

     

    - History-Archaeological institute of Mongolian Academy of Science,

    - Ulaanbaatar university,

    - Mongolian University of Science and Technology,

    - Mongolian National Museum-Joint team of International institute for investigation of nomadic civilization with representatives of local citizens. This team became the largest and national research team in archaeological history of Mongolia and rescued 440 archaeological findings. These findings are:

     

    • Stone weapon – 9

    • Slab grave – 55

    • Khirgisuur – 85

    • Habitation site – 1

    • Xiongnu burial– 62

    • Sacrificial feature-106

    • Mongol burial – 36

    • Monument with Tibetan script - 23

    • Neolithic burial - 4

     

    Open archaeological exhibition and research conference was held at National Museum of Mongolia with selected findings from 2014 and 2015. All above-mentioned findings will be accommodated in a museum that will be built near the dam of EGHPP. In 2015, Institute of History-Archaeological researchers conducted study on ethnographic research /local tradition, lifestyle, industry, culture, folk art features/ in the potentially affected area near the project site.

DAM SITE
  • THE DAM SITE IS LOCATED
    2.5 KM FROM THE CONFLUENCE OF THE EG-SELENGE river in KHUTAG-UNDUR SOUM, BULGAN PROVINCE.
RESERVOIR
  • NORMAL WATER LEVEL
    910 M A.S.L
  • VOLUME AT NORMAL WATER LEVEL
    5.7 BILLION m3
  • SURFACE AREA
    154.3 KM2
DAM
  • DAM CREST LEVEL
    912 M A.S.L
  • DAM CREST WIDTH
    8 м
  • DAM CREST LENGTH
    740 M
  • DAM HEIGHT ABOVE NATURAL GROUND
    82 м
  • DAM VOLUME
    2.29 MILLION m3
POWER HOUSE
  • INSTALLED CAPACITY
    315 МW
  • ANNUAL ELECTRICITY PRODUCTION
    606 MILLION KWh
  • TURBINE
    FRANCIS 4 X 68.78 MW, 2 X 20.5 MW, 1 X 3 MW
PROJECT INFRASTRUCTURE
  • FROM THE DAM SITE TO THE ERDENET SUBSTATION
    72.3 KM DOUBLE CIRCUIT 220KV TRANSMISSION LINE
  • FROM THE DAM SITE TO THE ERDENET CITY
    71.9 KM ACCESS ROAD, 320 M LONG REINFORCED CONCRETE BRIDGE OVER THE SELENGE RIVER
Scroll up