- NR.
- CONDUCTED STUDIES
- DATE
- CONTRACTOR
- 1
- Power market survey
- 2014.04 - 2014.07
- TRACTEBEL ENGINEERING
- 2
- Egiin Goliin HPP's regime
- 2014.04- 2014.07
- NATINOAL DISPATCHING CENTER
- 3
- Egiin Goliin HPP's economic profitability when operating alongside of CES, conclusion
- 2014.05 - 2014.06
- NATINOAL DISPATCHING CENTER
- 4
- Hydrology and meteorology study
- 2014.04 - 2014.08
- TRACTEBEL ENGINEERING
- 5
- Water and energy estimation
- 2014.04 - 2014.05
- TRACTEBEL ENGINEERING
- 6
- Geological survey
- 2014.05 - 2014.06
- TRACTEBEL ENGINEERING
- 7
- Geophysical survey
- 2014.04 - 2014.08
- TRACTEBEL ENGINEERING
- 8
- Seismic hazard assessment
- 2014.06 - 2014.07
- GEOTER LLC
- 9
- Topographic survey
- 2014.06 - 2014.07
- TRACTEBEL ENGINEERING
- 10
- Study of ice phenomena
- 2015.01 - 2015.02
- TRACTEBEL ENGINEERING
- 11
- Impacts of the Egiin Goliin HPP to the Selenge river and lake Baikal
- 2014.12 - 2015.03
- TRACTEBEL ENGINEERING
- 12
- Project optimization
- 2014.04 - 2014.08
- TRACTEBEL ENGINEERING
- 13
- Access road study
- 2014.03 - 2014.08
- MCPCGR LLC
- 14
- Transmission line study
- 2014.03 - 2014.06
- BAYSALTUGS LLC
- 15
- Technical specification
- 2014.04 - 2014.08
- TRACTEBEL ENGINEERING
- 16
- Construction schedule
- 2014.07 - 2014.08
- TRACTEBEL ENGINEERING
- 17
- Financial and Economical evaluation
- 2014.07 - 2014.08
- TRACTEBEL ENGINEERING
- NR.
- CONDUCTED STUDIES
- DATE
- CONTRACTOR
- 1
- Detailed environmental impact assessment
- 2014.04 - 2014.10
- ЕNCO LLC / ECOS LLC
- 2
- Studies of historical and cultural-archaeological study
- 2014.06 - 2014.07
- RESCUE TEAM
- 3
- Fish and aquatic life habitat study
- 2014.04 - 2014.12
- TAIMEN CONSERVATION FUND
- 4
- Paleontological study
- 2014.04 - 2014.05
- PALEONTOLOGICAL CENTER
- 5
- Resettlement
- WORKING GROUP
- 6
- Study of trees, bushes and shrubs
- 2014.03 - 2014.05
- FOREST R&D CENTER
DAM SITE
-
THE DAM SITE IS LOCATED
2.5 KM FROM THE CONFLUENCE OF THE EG-SELENGE river in KHUTAG-UNDUR SOUM, BULGAN PROVINCE.
RESERVOIR
-
NORMAL WATER LEVEL
910 M A.S.L -
VOLUME AT NORMAL WATER LEVEL
5.7 BILLION m3 -
SURFACE AREA
154.3 KM2
DAM
-
DAM CREST LEVEL
912 M A.S.L -
DAM CREST WIDTH
8 м -
DAM CREST LENGTH
740 M -
DAM HEIGHT ABOVE NATURAL GROUND
82 м -
DAM VOLUME
2.29 MILLION m3
POWER HOUSE
-
INSTALLED CAPACITY
315 МW -
ANNUAL ELECTRICITY PRODUCTION
606 MILLION KWh -
TURBINE
FRANCIS 4 X 68.78 MW, 2 X 20.5 MW, 1 X 3 MW
PROJECT INFRASTRUCTURE
-
FROM THE DAM SITE TO THE ERDENET SUBSTATION
72.3 KM DOUBLE CIRCUIT 220KV TRANSMISSION LINE -
FROM THE DAM SITE TO THE ERDENET CITY
71.9 KM ACCESS ROAD, 320 M LONG REINFORCED CONCRETE BRIDGE OVER THE SELENGE RIVER